Civils Reinforced concrete · [Your city]
Quarry Road retaining wall
- Programme
- 9 weeks
- Structure
- Groundworks
- Contract
- Measured
- Completed
- Apr 2023
The brief
A stone retaining wall along forty metres of lane had started to lean after a wet year, with a house garden behind it and the lane's only footway in front.
The engineer wanted a reinforced concrete cantilever wall; the residents wanted to keep using the lane.
What we did
We worked in six-metre bays: dig, shutter, pour, strike, backfill, move on. The lane stayed open to one lane of traffic with lights, and the footway was closed one bay at a time. The old stone was cleaned and reused as the facing, so from the lane it still looks like the wall that was there.
The result
Nine weeks, no full closure, and the garden behind lost a metre less than the first scheme would have taken.
Job sheet
FW-0271- Client
- [Highways authority]
- Architect
- Not applicable
- Engineer
- [Practice name]
- Site manager
- [Name]
- Variations
- 0
Services on this job
- Traffic management
- Excavation
- Reinforced concrete
- Stone facing
- Drainage
Programme
- Ground
- Frame
- Envelope
- Fit-out
- Handover
Jan 2023 – Apr 2023 · 9 weeks, on the contract week.