Civils Reinforced concrete · [Your city]
Mill Lane culvert
- Programme
- 14 weeks
- Structure
- Highways
- Contract
- Measured
- Completed
- Jun 2025
The brief
A Victorian brick arch carried the lane over a stream and backed up every winter.
The highways authority wanted it replaced with a precast box culvert and a new deck, under a twelve-week closure that could not slip because the diversion ran past a school.
What we did
We diverted the stream through a temporary flume, broke out the arch in three days and poured the base slab on week three. The culvert units were set in a morning, then the wing walls, the deck and the parapets. The road was reopened for the school run on the Monday of week twelve; the last two weeks were landscaping and the stream bed.
The result
Reopened on the day in the closure notice. The flume stayed in longer than planned after a wet April, and that was the only change to the method.
Job sheet
FW-0360- Client
- [Highways authority]
- Architect
- Not applicable
- Engineer
- [Practice name]
- Site manager
- [Name]
- Variations
- 1, weather
Services on this job
- Stream diversion
- Demolition
- Reinforced concrete
- Precast culvert
- Road deck and parapets
- Landscaping
Programme
- Ground
- Frame
- Envelope
- Fit-out
- Handover
Feb 2025 – Jun 2025 · 14 weeks, on the contract week.
Site photos
-
Week 03 · Groundworks -
Week 01 · Groundworks