An aerial view of a large industrial site with cranes and the first steel going up

Commercial New build · [Your city]

Northgate Logistics

Floor area
4,800 m²
Programme
38 weeks
Structure
Steel portal frame
Contract
Fixed price
Completed
Mar 2026

The brief

A distribution shed with six dock doors and a two-storey office block on its front, on a site the client had bought next to the unit they were outgrowing.

The hard part was the brief's last line: the old unit had to keep trading, with lorries in and out all day, until the new one was ready.

What we did

We split the site with a haul road and a fence on day one and kept them for the whole job. Ground was poor, so the slab sits on piles and a ground beam grid. The portal frame went up in three weeks with two cranes, the cladding followed a bay behind it, and the office block was fitted out while the yard was being laid.

The result

The client moved over a weekend. The old unit was cleared the following week and the yard extended across it, which was the only piece of the programme we moved.

Job sheet

FW-0398
Client
[Company name]
Architect
[Practice name]
Engineer
[Practice name]
Site manager
[Name]
Variations
4, three client-led

Services on this job

  • Piling and ground beams
  • Steel portal frame
  • Cladding
  • Office fit-out
  • Yard and drainage

Programme

  1. Ground
  2. Frame
  3. Envelope
  4. Fit-out
  5. Handover

Jun 2025 – Mar 2026 · 38 weeks, on the contract week.

Site photos

  • Steel portal frames and roof purlins of the new shed
    Week 12 · Frame
  • A tower crane against the evening sky above the frame
    Week 10 · Frame
  • The concrete gang levelling the slab pour
    Week 03 · Groundworks