“Fixed price” is the phrase every client wants to hear and the one most often misunderstood. It does not mean the number can never change. It means the number is fixed for a defined piece of work, and that everything outside that piece is dealt with in the open.

What the sum covers

The sum in your contract is priced from a set of drawings and a specification, listed by name and revision on the first page. Everything those documents describe is in the sum: the foundations the engineer drew, the windows on the schedule, the kitchen in the specification. If a wall is on the drawing, it is in the price, whether or not we noticed it when we priced.

That last part is the point. A fixed price moves the risk of pricing badly from you to us. If we underestimated the bricks, that is our problem.

Where it can move

Three things change a fixed sum, and all three should be written down before the work happens.

  • A change you ask for. A second rooflight, a different floor, a bigger terrace. We price it, you agree it, it becomes a variation.
  • Something nobody could see. An old tank under the garden, rock where the survey said clay. The contract says how this is handled, usually at rates listed in it.
  • A provisional sum. An allowance for something that was not designed when we priced, such as the kitchen or the landscaping. When the design arrives, the real cost replaces the allowance, up or down.

If a contractor tells you none of these can ever happen, ask them where the risk went.

Reading the provisional sums

Ask for the schedule of provisional sums before you sign, and read it as a list of decisions you have not yet made. A contract with a small sum and a long list of allowances is not a fixed price; it is an estimate wearing a suit. A short list with realistic allowances is what you want.

For each line, ask two questions: what is the allowance for, and when do I need to decide? Our Friday report carries that list from the first week, with a date against each item, so no allowance turns into a surprise.

The honest version

A fixed price fixes the work on the drawings, at the sum on the contract, for the programme on the first page. It does not fix the weather, the ground or your mind. What it does is make every one of those visible, priced and agreed before anyone picks up a tool.