The programme is the page of your contract most people skip. It is a chart of bars, one per task, laid across the weeks of the job. Here is how to read it in five minutes.
The bars
Each bar is a task: groundworks, frame, roof, first fix. Its left end is the week the task starts, its right end the week it finishes. Tasks that happen at the same time sit above one another. A line joining the end of one bar to the start of another means the second cannot start until the first is done: you cannot plaster a wall that has not been wired.
The critical path
Some tasks have room to slip without moving the end date. Others do not. The chain of tasks with no room is the critical path, and on a house it almost always runs through the frame. If the frame goes up a week late, the roof goes on a week late, the building is watertight a week late, and the plasterers, who were booked for a date, arrive to find wet walls.
That is why we treat the frame week as the fixed point of the whole job. Window sizes, the frame design, the crane booking and the road closure for it are all confirmed weeks ahead, and the decision list in the Friday report shows a countdown to it.
Float
Float is the room a task has to slip. A task with two weeks of float can finish two weeks late without hurting anything. We put float into the programme on purpose, in the weeks that are usually wet and around the holidays, and we show it, so that a bar finishing later than planned does not look like a problem when it is not.
What to watch for is float being used up. When a task on the critical path has none left and is still slipping, the end date is moving, and we say so in the report that week rather than at the end.
The milestones
Four dates on the programme matter more than the rest: the day we start on site, the frame week, the day the building is watertight, and handover. Put those four in your diary. Everything else on the chart exists to protect them.