Every slab we pour is photographed the morning before the concrete arrives, from four corners and above, with a tape in the frame. It takes twenty minutes. It is the most valuable twenty minutes of the job.
What the photograph proves
Once the concrete is in, the reinforcement disappears for the life of the building. Nobody will ever see again whether the bars were the right size, at the right spacing, with the right cover to the edge, sitting on chairs and not on the ground. The photograph is the only record that they were.
Three people will ask for it:
- The engineer, who signs off the steel before the pour and wants to see what was signed.
- The insurer, if there is ever a crack and a question about whose fault it was.
- The next owner, whose surveyor will ask what is in the slab and be told, in most houses, that nobody knows.
How we do it
The engineer’s inspection comes first; the photographs are taken after any changes they ask for, so they show what was poured and not what was planned. Each shot has the date and the grid line on a board, and the set goes into the Friday report that week and into the handover file at the end.
We do the same for every drain run before it is backfilled, every steel beam before it is boarded in, and every wall before it is plastered. The handover file for a house runs to a few hundred photographs, and it is the part of the job clients come back to most.
The habit behind it
Photographing the steel is a small thing. The habit it comes from is not: nothing on our sites is covered up without a record of what was underneath. It keeps the gang honest, it keeps the engineer calm, and years later it answers the question that would otherwise cost someone a core drill.